Exposed Sewer Lines Near Audubon ‘Health Hazard Waiting to Happen’, RestonNow, January 29, 2016

RestonNow's Karen Goff provides an excellent over view of the RA Board discussion of the eroded ravine near South Lakes High School, including exposed sewer lines, and the initiative Reston Association is taking to correct the problem. 

Here are a couple of excerpts from the article:
Erosion has contributed to the exposure of eight sewer line in the hillside leading from South Lakes Drive to Lake Audubon. If significant action is not taken, Reston could face serious environmental and public health situation.
That was the takeaway from a long discussion at Reston Association’s Board of Directors meeting Thursday, where the board passed several motions to commit money to study the issue and continue pressing Fairfax County officials to act on the issue.
“This is a health health hazard waiting to happen,” said RA land use attorney John McBride, who warned that recent events in Flint, Mich., where a money-saving effort to change the water supply resulted in dangerous lead contamination. . . .
At issue is stormwater runoff that starts at South Lakes High School and Langston Hughes Middle School, goes under South Lakes Drive and then through a steep drainage ditch running between Wakerobin Drive and Cedar Cover Cluster, emptying into Lake Audubon.
Years of runoff have contributed to significant erosion, which has left eight sewer pipes exposed, said Charles Smith of the Fairfax County Department of Public Works and Environmental Services. . . .
For the rest of this article, click here. 

Tuesday, October 20, 2015

Reston 20/20 Testimony on South Lakes High School Addition



 Statement of Terry Maynard, Reston 20/20 Committee re
Proposed FCPS Addition to South Lakes High School
Fairfax County Board of Supervisors
October 20, 2015


Good evening Chairman Bulova and members of the Board.  I am Terry Maynard, 2217 Wakerobin Lane, Reston, Virginia, and I am here representing the Reston 20/20 Committee, a committee of community volunteers that strives to protect the vision and planning principles laid out for Reston by the late Bob Simon and encapsulated in the Comprehensive Plan. 

I am here this evening to speak specifically about the proposed addition to South Lakes High School, a school just one block from my home.  There is absolutely no doubt that the classroom space that the School Board seeks is needed.  What is not needed, however, is the added destruction of neighboring private properties from the increased stormwater runoff the project will create, and ultimately the added pollution of the Chesapeake Bay.

As noted in the staff report accompanying the School Board’s proposal, FCPS has sought and received a waiver grandfathering its use of old and inadequate stormwater management standards, not the tougher standards you legislated last year.  The result will be additional stormwater runoff into the swale on the east side of South Lakes High School that drains from FCPS property under South Lakes Drive and into a stream between the residential areas downstream, specifically Cedar Cove cluster and Wakerobin Lane.  (See attached overview image.)

The experience of both downstream neighborhoods has been that each addition to the high school, including parking lots, has added to the stormwater flows from the east side of the high school property, especially during storms.  The stream from South Lakes High School’s property has turned a once smooth ravine floor with lush plant life into a 3-6 foot deep, 6-10 foot wide gash that floods out of its banks with each major storm along its 1,000 foot length and 30’ foot drop. 

While FCPS cites costs as the driver of its decision to stick with the old, ineffective stormwater management techniques and standards, there are dollar costs for the County, RA, and homeowners for FCPS not doing what it can to prevent damage.  Specifically:

  •  DPWES has already spent tens of thousands of dollars preventing and repairing leaks in its sewer line that runs the length of the creek.  It has deposited rip-rap three times in different places along the creek over the years, including backfilling a 12’ deep, 300’ long washout at the outlet of the stream that exposed two sewer lines.  DPWES also had to make emergency repairs this July when its sewer line ruptured, resulting in at least 100 gallons of raw sewage spilling into the stream and lake.   Now, DPWES is assessing the stream for a complete stormwater remediation project at a cost we can only guess will exceed a million dollars if it is approved. 
  • Reston Association is planning to clear scores of mature trees on its property in the ravine to prevent future sewer line breakages from fallen trees, a cost that will reach into the tens of thousands of dollars.  And it has cleared many such trees in the past.
  • Homeowners have paid to double-wrap their laterals in an effort to reduce the risk that one of them may break at a cost of a couple of thousand dollars each.  One Wakerobin resident had to remove a gazebo on her property that had been undermined by the expanding stream bed.  RA is also planning to require that homeowners remove their trees that may fall into the creek at a likely cost exceeding one to several thousand dollars per household depending on how many trees are removed.

 All these costs stem from the stormwater flows coming from South Lakes High School property. 

And all of this may blow back on the County.  An attorney has pointed out to Reston 20/20 that, by discharging additional stormwater onto downstream private property without permission, FCPS may have committed trespass and may be responsible for the damages it has caused and will cause by the discharge of additional stormwater from the proposed project.  The trespass could result in a suit by RA or individual homeowners for injunctive relief, damages, and the requirement to undertake the required restoration caused by its unauthorized actions.  He added that the inadequacy of the FCPS plans for the school addition could also compromise the integrity of any related County bonding action. 

That said, Reston 20/20 strongly recommends that the Board of Supervisors defer a decision on the South Lakes High School addition proposal until the County Attorney has provided a legal opinion that the FCPS proposal to implement a minimal stormwater management program does not create an unnecessary legal or financial risk for the County.   In the meantime, we believe the Board should also press FCPS to be a responsible Reston community partner and environmental steward in addressing the problem it created, consistent with its own Student Achievement Goal #3 (“Demonstrate Responsibility to the Community and the World”) and Reston’s Planning Principle #2 (“Planning will provide for environmental sustainability and green technology.  Natural resources and ecosystems, including natural areas, will be protected and restored. . . .”)  With a true “best practices” stormwater management plan for its proposed addition, FCPS can reduce any legal threat and demonstrate its commitment to the Reston community. 

Sunday, October 18, 2015

Maynard-Hynes e-mail exchange re FCPS Failure to Meet Environmental Quality Standards in Proposed South Lakes High School Addition


From:  Hynes, Patricia (School Board Member)

  •  
  • 10/18/15 at 7:02 PM
  • Message body

    Mr. Maynard,

    I hope I didn't offend you by replying on Reston Now. I noticed that Karen Goff mentioned your email to me, so I thought it made sense to let her readers know I had responded and how. I think Reston Now can be a good forum for conversations like that. I won't publish this email - I don't think it will add much to what's already been said.

    I am sorry the school system can't do more. I wish we could exceed minimal requirements on all measures of environmental stewardship. Our new construction now meets very high energy conservation and sustainability standards, but we can't afford to retro-fit older buildings. FCPS was recently recognized for having more "Energy Star" certified buildings than any other school district in the country, but we have no plans currently to replace fossil fuel sources with alternatives because of high up-front costs. We use permeable parking surfaces where it helps to meet requirements, but we can't justify putting them everywhere, even though they're clearly preferable for the environment.

    Our hands are tied in these and many other ways by the inadequate capital funding the schools receive. Where we can, we work with the county. One area of collaboration is  stormwater management, for which there are designated county funds because we all pay an extra fee in our water bills.

    I don't know if this interests you, but I would love to show you what we CAN do. We have exciting environmental stewardship education programs in all of our schools. Terraset ES is a great example of what we can do when the educators in the building are encouraged to incorporate outdoor learning into new construction. Please let me know if you'd like a tour of Terraset, or any of the many other projects in Reston where our students are learning about stewardship by doing it.

    Pat

    Pat Hynes
    Fairfax County School Board
    Chair and Hunter Mill District Representative  
    From:  Terry Maynard   Today at 12:25 PM
    >>

    Dear Chairman (and Hunter Mill School Board Representative) Pat Hynes,

    I have just read the staff report for the proposed 40,000SF addition to South Lakes High School across the street from our home and found that it explicitly states that FCPS does not intend to meet Virginia's environmental quality standards for stormwater remediation during the construction of the proposed addition. 
    Specifically, here is what the staff report says (p.14):
    Staff notes the applicant has received approval of a general permit through the Virginia Department of Environmental Quality (DEQ), which allows for the applicant’s proposal to be grandfathered under the old stormwater management requirements prior to the Board’s adoption of the new stormwater ordinance in 2014.
    So, in a Reston community that focuses on sustainability and environmental excellence, FCPS is proposing to meet old, much less stringent stormwater management requirements than is the current standard, presumably so it can save a few dollars.

    The proposed addition of some open joint parking surfaces (one of which is on the wrong side of the high school) and filterra structures is grossly inadequate to meet the additional flow caused by the addition, much less the current unacceptable stormwater management conditions.

    In and of itself, this position by FCPS is not worthy of a school system that claims to focus on excellence, but it is especially heinous when the School Board's disregard for stormwater management standards has been causing serious environmental consequences for two neighborhoods south of South Lakes Drive--Wakerobin and Cedar Cove--where SLHS has been dumping heavy stormwater flows for nearly four decades.  Moreover, those consequences have never figured into the school's building or several additions beyond the minimum required by law (or even lower standards in previous laws).  In fact, each new school addition has made the situation worse for these neighborhoods because of the inadequacy of the stormwater remediation effort and the  disregard of the impact of school construction on the surrounding area.  Even the FCPS/County effort to remediate flooding in the basin above South Lakes Drive this summer added to the stormwater problem by accelerating the pace of drainage from school property into the stream below.

    Most of the stormwater from both SLHS and Langston Hughes Intermediate School collects in a basin to the east of the high school and then flows through a stormwater tunnel under South Lakes Drive.  The resulting stream then plunges about 30' in its 1,000' flow to Lake Audubon.  During storms, the creek experiences massive erosion and the generation of huge quantities of silt that is spewed into Lake Audubon as the force of the flow cuts the stream wider and deeper.  The decades-long problem has exposed both the County sewer in several places as well as several residents' lateral connections.  In fact, this summer the force of the flow actually broke a County sewer line requiring emergency repairs and dumping raw sewage into Lake Audubon.  (Please see the two attached videos.  One shows the County sewer line that broke this summer during a major storm runoff caused by the failure of school stormwater remediation efforts.  The other shows the velocity of the flow coming out of the South Lakes Drive tunnel from FCPS property during the same timeframe.)

    Once its own sewer line broke, the County saw the problem caused by these stormwater flows.  Nonetheless, this problem was first brought to Supervisor Hudgins' attention in a creekside discussion with some Wakerobin residents in 2004--eleven years ago.  RA, Cedar Cove, and Wakerobin residents have all tried repeatedly to pursue County action in remediating the problem over the last decade to no avail--until the County sewer line broke.

    As a result, Supervisor Hudgins sponsored a meeting on the problem this passed Tuesday although no FCPS personnel attended.  As presented to the two neighborhoods by DPWES staff, it will take at least three years, probably more, for County action beginning now to actually result in a well-controlled stream runoff--if the project even gets approval by the Board of Supervisors.

    Both neighborhoods want faster action because of the potential for further envionmental damage from erosion, silting, or even another sewer leak into the lake.  Both neighborhoods believe (on a firm foundation) that the problem originates on FCPS property and efforts to remediate the creek problem will not succeed unless FCPS takes further action above.

    I believe now is the time for the School Board to step up and be an environmentally aware good neighbor and (a) fulfill its obligation to meet contemporary stormwater management standards at the minimum and (b) contribute (if not lead) the effort to remediate the serious stormwater problem the two neighborhoods are facing on both sides of South Lakes Drive because of FCPS' failure to take needed action.

    As our representative to the School Board and advocate for the addition to South Lakes High School,  I specifically look to you to lead that effort to become a better school and a better neighbor.

    Thank you for your favorable consideration of this serious environmental situation.

    Sincerely,
    Terry Maynard
    2217 Wakerobin Ln
    Reston, VA 20191
    703-476-5376

    BCC:  Wakerobin and Cedar Cove neighbors


    Friday, October 16, 2015

    FCPS ignores current stormwater management standards and downstream damage in South Lakes High School expansion proposal.

    In their report on the much-needed proposed 40,000 SF addition to South Lakes High School (SLHS), the County planning staff note that Fairfax County Public Schools (FCPS) does not plan to meet current stormwater management standards approved just a year ago.  Instead, they obtained a waiver from the state Department of Environmental Quality (DEQ) to use earlier, less stringent requirements.  Here is what the staff report says:
    Staff notes the applicant has received approval of a general permit through the Virginia Department of Environmental Quality (DEQ), which allows for the applicant’s proposal to be grandfathered under the old stormwater management requirements prior to the Board’s adoption of the new stormwater ordinance in 2014.
    By using this waiver, FCPS will contribute even further to the erosion, silting, and--most recently--raw sewage release into Lake Audubon as a result of the massive stormwater flows from SLHS property through a ravine south of South Lakes Drive.  The stormwater releases have cut through the natural ravine surface to a depth of more than twelve feet near the mouth of the creek, forcing the County's public works department (DPWES) to rebuild the bottom and shoreline with very large rip-rap (large boulders to protect the shoreline).  DPWES has also had to add rip-rap at two places farther upstream where its sewer line is also exposed, but the torrents from SLHS have eroded the base underneath those simple fixes so the sewer line is hanging several feet above the ravine's base.  Three residential laterals connected to the sewer line are also exposed and suspended and are at risk of breaking (although two neighbors have reinforced their laterals by double-wrapping them with high-strength pipes).

    The erosion and silting problem has gotten worse with every addition to SLHS in its near-40 year history.  The addition to the high school a decade ago included the addition of more than 100 asphalt parking spaces on the east side of the school, and the larger impermeable surface added to the flow into the basin to the east, through the tunnel under South Lakes Drive, and plunging down the ravine to Lake Audubon.  This summer, FCPS tried to remedy the flooding in the townhouse development on the other side of the basin caused by the additional runoff from its parking lot.  In so doing, it accelerated the flow through South Lakes Drive tunnel, turning the downstream side of the tunnel into a spigot throwing large volumes of stormwater at high speeds down the steep incline to Lake Audubon (30' drop in 1,000').  One consequence, in a recent storm, the County sewer line that runs along and across the ravine broke, spewing raw sewage into the stream and the lake.

    It was only at that point and with pressure from RA leaders that Supervisor Hudgins agreed to begin a process to see how the stormwater problem might be remediated.  The first step in that process was a meeting with the community, specifically the two neighborhoods--Cedar Cove and Wakerobin--directly affected by the eroding stream.  It was no surprise that no one from FCPS attended the meeting.  At that meeting, held on Tuesday evening at RA headquarters, DPWES personnel laid out the process through which such a remediation project must go.  Suffice it to say, it will be at least three years and maybe five before the stream below South Lakes Drive will be repaired--and that's if the project makes the budget cut.

    Community members highlighted that the problem originates with the repeatedly inadequate effort of FCPS to control the stormwater flow on its property across the street, and that the problem won't be solved until FCPS stops the torrential flows, an outcome impossible with its current plan for the SLHS addition.  The community also highlighted that this problem has been a continuing for years and was brought to Supervisor Hudgins attention in a creekside meeting at least eleven years ago.  It is time to set a side the normal business process and accelerate the remediation effort starting with completing the assessment and design process in time to seek full funding for construction in the next fiscal year.  That was left for further consideration.

    RA leaders promised to follow up on the community meeting with Supervisor Hudgins by the end of the month.

    Separately, Terry Maynard, among the Wakerobin homeowners affected by the creek's deterioration, sent a letter to FCPS Board Chairman and Hunter Mill District Representative Pat Hynes detailing the problem, FCPS' continuing refusal to address it in any meaningful way, and calling on her and FCPS to at least meet the requirements of the current County stormwater management ordinance and possibly even take leadership in remediating the stream.  No response has been received yet.

    Below are two short videos showing the water flows a day after a major recent downpour.  One shows the repaired sewer pipe (light blue wrapping) in the midst of the flow.  The other shows the water tumbling from the South Lakes tunnel down the stream below. 


     


    Wednesday, October 7, 2015

    Upcoming Hearing on Proposed 40,000 SF Addition to South Lakes High School

    The first item on the Fairfax County Planning Commission's agenda for its October 15, 2015, meeting at 8:15PM at the Fairfax County Government Center auditorium is a proposed 40,000SF addition to South Lakes High School.

    The construction of the addition would result in a total gross floor area of 373,750 square feet.  The purpose of the addition is to provide additional classroom to increase the capacity of the existing school from 2,126 students to 2,500 students.  Along with the building addition, the School Board proposes the addition of 128 parking spaces raising the total number of spaces to 758.  In addition, the Board proposes to modify stormwater management by installing open joint pavement blocks and five filterras.  The School Board also proposes waiving transitional screening requirements on the west, north, and east sides of the school. 

    The high school clearly needs additional capacity to handle the number of students as the large number of modular schoolrooms there highlights.  At the same time, there may be concerns about:
    • Additional traffic, especially during the morning rush hour, as students and faculty attempt to enter the school's parking areas.
    • Stormwater issues, which have been a decades-long problem for neighbors east and south of the school, just partially corrected north of South Lakes Drive this year.
    • Waiving of screening requirements will create an additional noise issue for residential areas east and west of the school.
    If you wish to speak at the hearing, the instructions for registering and speaking are available here under "Meeting Information."

    Here a perspective drawing and an annotated overview plan of the proposal. 





    The full 54-page proposal is available here for review.