Phase 1 of Dulles Metrorail 67 Percent Complete, Connection Newspapers, April 4, 2012

Phase 2 hits a snag as Loudoun County Supervisors debate opting out.

VDOT officials delivered good news and bad news on the 23-mile Dulles Corridor Metrorail project during a news conference March 29 at the VDOT Virginia Megaprojects office.
The good news: crews took full advantage of the mild winter and pushed phase 1 construction of the Silver Line to nearly 70 percent completion. . .
. . .  The bad news: phase 2 of the project – which is planned to extend into Loudon (sic) County and provide a one-seat, no-transfer ride from Dulles Airport to downtown Washington – may come to a screeching halt. . . .
Read the rest of this article here.  