Rob Whitfield, Dulles Corridor Users Group, wrote a detailed
letter in last week's Fairfax Times noting that there are several important unresolved issues in the financing of the Silver Line. A breakdown in any of these issues could result in a failure to obtain $1.9 billion in low-cost TIFIA financing, and thereby undercut the reductions in tolls that MWAA, elected officials, and others have been recently been pounding their chests about. We present below his letter with the
updates highlighted in red.
Despite all the hoopla about
the Metropolitan Washington Airports Authority (MWAA) turning over
control of Dulles Rail Phase 1 to the Washington Metro Area Transit
Authority (WMATA), several major unresolved issues remain:
1.
We
have yet to see the proposed business terms and conditions for the
Dulles Rail Transportation Infrastructure Finance and Innovation Act
(TIFIA) loan. A U.S. Department of Transportation official said last
week that the public would not be allowed to see the agreement until
after all terms have been negotiated and an agreement signed. This
exemplifies the approach of former House Speaker Nancy Pelosi to
government actions: “We have to pass the bill so that you can find out
what is in it.”
The
TIFIA Program is governed by the Federal Credit
Reform Act of 1990 (FCRA), which requires the U.S. Department of
Transportation to establish a capital reserve, or “subsidy amount,” to
cover expected credit losses before it can provide TIFIA credit
assistance. Congress places limits on the annual subsidy amount
available.
Moving
Ahead for Progress in the 21st Century Act (MAP-21) authorizes $750
million in FY 2013 and $1 billion in FY 2014 in TIFIA budget authority
from the Highway Trust Fund (HTF) to pay the subsidy cost of TIFIA
credit assistance. An MWAA financial advisor for
the Dulles Rail project indicates that the capital reserve required is
typically only 10% of the total TIFIA credit assistance amount. He
expects closure before September 30, 2014 but if a delay in closure
occurs, given the potential for the HTF to run out of funds later
in 2014, the public should not assume that TIFIA credit assurance for
Dulles Rail is a certainty,
particularly at levels needed to complete the Dulles Rail project by
2018.
2.
MWAA has yet to fund any of its 4.1 percent Dulles Rail capital cost
share from Airport Revenues. Over five years have passed since Phase 1
construction started and months since Phase 2 work commenced.
Chairpersons Bulova and York plus Virginia officials have yet to demand a
specific MWAA payment plan. The 2007 Capital Cost Funding Agreement
provided no proposed schedule for MWAA payments to be made. Where were
our politicians?
Based on what was revealed at the MWAA Board meeting last month, it appears that some airlines
are balking at the proposed use of Passenger Facility Charges at Reagan
National to pay for MWAA’s share of Dulles Rail capital costs. Similar concerns exist at Dulles International Airport
where passenger charges are the highest in the region and among highest in the entire USA.
3.
The capital costs of Phase 2 within Dulles Airport will be at least $1
billion, including two stations. MWAA’s share of project cost
obligations set by the 2007 “agreement” remain under $250 million while
the future costs for Dulles Toll Road(DTR) users will skyrocket from
2006 projections made by MWAA - TIFIA notwithstanding. Why have our
political leaders not demanded that MWAA and WMATA pay a fair share of
overall capital costs? Is subsidizing those who live and work inside the
Capital Beltway more important to our politicians than the thousands of
dollars in additional tolls to be paid with after tax funds by those
who must rely on the Dulles Toll Road for commuting?
4.
MWAA next month plans to select the contractor for a $260 million
Dulles Maintenance facility to be built for maintenance and
storage of not only 128 Silver Line Series 7000 railcars being paid for
by MWAA (mostly from DTR funds) but at least one half of the 300
(planned 420) additional Series 7000 railcars to be delivered to WMATA
over the next five years.
Officials from
MWAA, WMATA and USDOT have been asked repeatedly for over two years,
when, if at all, are MWAA and WMATA going to negotiate for WMATA to pay
for its share of facility capital costs. Nobody wishes to acknowledge
responsibility for this matter.
5. MWAA has
yet to fulfill certain terms of its January 2006 proposal to the
Commonwealth to “Operate the Dulles Toll Road and Build Rail to Loudoun
County.” An audit should be conducted to confirm compliance by MWAA with
all provisions of the 2006 proposal.
6.
MWAA plans to lease land for development adjacent to the two Metrorail
stations on Dulles Airport property. This land is leased
from the federal government. MWAA intends for 100 percent of revenue
generated to be used solely to defray Dulles Airport expenses--with no
revenues to be used to offset DTR tolls needed for MWAA Dulles Corridor
Enterprise bonds. A MWAA Board member helped negotiate revisions to
Federal Aviation Administration Congressional funding provisions. It
appears possible that MWAA will be able to use its powers to benefit
airport development on terms detrimental to development of nearby land
whose owners pay property taxes. MWAA claims it pays fees in lieu of
taxes but no independent accounting of the adequacy of such fees appears
to have occurred.
These issues, and others, must
be resolved BEFORE Virginia funds the proposed $300 million in further
financial assistance, approved by the Virginia General Assembly in 2013,
to offset proposed toll cost increases. Remember, in 2006. MWAA claimed
that no further assistance would be needed
from the Commonwealth for the Dulles Rail project. Various MWAA
officials in office prior to 2010 lied repeatedly to Virginians about
costs and funds needed from DTR users. Why should we expect that the
lies won’t continue, particularly because the MWAA Board is controlled
by D.C. and Maryland political appointees who don’t give a flying fig
about the costs for Virginia taxpayers who live and work in the Dulles
Corridor.
The
failure of nearly ALL Virginia politicians, both Democrats and
Republicans, to address these matters in a timely manner is the last
straw in the series of outrageous failures in accountability by
everybody involved in Dulles Rail during the last decade. Maybe it
reflects the culture of corruption that pervades most political actions
in Richmond and Washington, D.C. as well as those taken by many or most
Northern Virginia elected officials.
Last
Friday the Dulles Corridor Advisory Committee met. In the past DCAC members have acted as a rubber stamp to MWAA proposals. Unfortunately, DCAC members continued to shirk their obligations to those who live and work in the Dulles Corridor as they have since 2006 by not insisting on answers to these issues.
Rob Whitfield, Dulles Corridor Users Group
No comments:
Post a Comment
Your comments are welcome and encouraged as long as they are relevant, constructive, and decent.