Michael Neibauer writes:
When it comes to the Silver Line project, even a $300 million investment isn’t enough to get answers.
Loudoun County 
will pay for more than 10 percent of the $2.778 billion extension of the
 Silver Line from Reston to Ashburn — or 4.8 percent of the $5.7 billion
 combined Phase 1 and Phase 2 price tag. But the county has very little 
role in, or even knowledge of, the project itself, according to a staff 
report. That includes major decisions such as schedule, cost and design 
changes. . . 
The frustration bubbled to the surface in 
late April, when MWAA publicly announced that stormwater management and 
technical design changes would delay the opening of the 11.4-mile Silver
 Line Phase 2 by roughly 13 months.   (Reston 20/20 note:  And we have learned since that the stormwater issue accounts for only one month of the 13-month delay.)
The decisions were all made, Loudoun staff says, by MWAA and contractor Capital Rail Constructors (led by 
Clark Construction Group LLC
 and Kiewit Infrastructure South Co.) during a “six-month effort of 
schedule development and negotiations” in which neither Loudoun nor 
Fairfax had any role. Loudoun received a revised schedule in mid-May, 
indicating a late 2019 or early 2020 launch for passenger service, but 
it still has not been provided a new cost estimate or any word of the 
increased construction costs resulting from the design changes. . .
 
Both Loudoun and Fairfax, according to Loudoun staff, “were again 
excluded from schedule impact discussions” between MWAA and its 
contractor, the development of a revised schedule, and ongoing 
discussions regarded additional costs resulting from the massive 
stormwater management redesign. . . .
Click here for the rest of Mr. Neibauer's article. 
 