Terry
Maynard
Things were looking promising
last summer for opening the Silver Line.
We might actually have Metrorail service in Reston by the end of 2013 as
promised repeatedly since the project began.
A sign of the times. (RestonNow) |
Then the project timeline
derailed, so to speak.
The start of Silver Line operations
is now three months overdue and no one involved with the line’s construction is
willing even to speculate when service will begin. Press reports say that start-up
has been delayed “indefinitely.” Supervisor
Hudgins has said she would be “very disappointed” if operations were not
begun by the end of summer. Yet, there
is the distinct possibility that the Silver Line won’t open to Reston until
2015—more than a year late. How many millions of dollars over budget and
who will pay those sums remain huge unknowns despite contract terms putting
cost overruns on the contractor and the project manager, MWAA.
We first got a hint of significant
construction schedule issues to come when two
test trains knocked handrails and emergency shutoff switches, reportedly
installed in the wrong place, off the wall of the rail tunnel in late 2012. How does
a competent contractor on a multi-billion dollar project put handrails and
switches in the wrong place?
Nonetheless, assurances were given that there was nothing wrong with the
tunnel even though an inch of settling in the tunnel floor had been reported a
year before these incidents.
And press reports kept
dribbling out last spring that there were problems with the line’s
Automatic Train Control (ATC) system, including unauthorized changes in the
design by its builder, Alstom Signaling.
The ATC system controls train movement and ensures proper spacing
between trains. The failure of the ATC
system on Metro’s Red Line killed
nine people and injured dozens more in 2009 when one Red Line train plowed
into another. Neither MWAA nor the contractor would confirm
the ATC problems.
Fatal Metrorail Red Line accident, 2009. (Washington Post) |
In May, MWAA officials were saying the project
was on schedule to open in December. The
builder’s project executive director said it was 98% complete. In June, MWAA CEO
Jack Potter even said the project would be ready to turn over to WMATA on
September 9, allowing WMATA’s 90-day test and training period before opening in
December—on schedule.
Then, July 17, the schedule lurched. MWAA
announced “that the expected substantial completion of Phase 1 of the
Metrorail Silver Line project would be delayed by approximately eight
weeks.” Neither MWAA nor the contractor would
say what caused the delay. At the
outside, that meant the project would be ready for turnover to
WMATA—“substantially complete”—by the end of October or early November.
October and November passed
without “substantial completion” or an explanation.
MWAA finally confirmed in a December 2, 2013, press release that
continuing failures in updates to the ATC software would cause further completion
delays. No other problems were
identified and no date for completion was set.
Maybe early 2014.
At first, some good news. In early February, the
contractor declared that work on the project was “substantially complete.” MWAA had 15 days to review the contractor’s
work and certify that it was satisfied that it could turn the project over to
WMATA. WMATA would then have a 90-day
period of final testing and training of train operators before beginning service
to Reston.
But that didn’t happen. In a
February 24 press release, MWAA and WMATA “determined the contractor has
not yet met the contract requirements for substantial completion.” In fact, the contractor failed to meet contract
requirements in seven of the 12 areas of review. Some were nuisance issues, but the ATC
continued to have “performance issues” and MWAA noted a“(f)ailure to fully
correct defects that impact operations, including track gage problems.” What? They couldn’t lay the tracks right?
Yet, now, a month later, nothing
has been done.
And the atmosphere turned stormy
this week. Threats of multi-million
dollar fines are in the air if the project is not “substantially complete” by the
April 9 contract deadline. The lead
contractor blames MWAA, saying, “MWAA has yet to specify what it believes
needs to be done before we can re-submit the substantial completion
package.” MWAA
says it has been meeting several times daily with the contractor to work
out the issues. The
contractor has also hinted that the deadline—and the fines that would
follow—may be negotiable, apparently looking for a plea bargain deal. On the other hand, former Congressman Tom
Davis, now an MWAA Board member and Chairman of its Dulles Corridor Committee,
called the situation “a
soap opera” and is threatening
a lawsuit for liquidated damages if
the contractor does not meet the deadline.
These interactions are rapidly turning
away from “good faith” discussions among engineers and technicians solving
construction problems. They are becoming
a standoff between accountants and attorneys for the two sides who are more
interested in evading responsibility for failures and added costs than getting
the job done. They certainly aren’t driven
by meeting a budget or a schedule. Most importantly, they do not appear to have
even a hint of the broader public interest in mind.
Reston wants its Silver Line rail line service now, even though it will
be impossible for service to begin in the first half of the year.
And we don’t want to pay for the shortcomings of either or both of the
parties to this growing construction delays.
It is past time for our elected
leaders, county, state, and federal,
to press both MWAA and Bechtel, reminding them whose money they are spending
and whose rail service they are supposed to provide. They have been missing in action as this
fiasco unfolds.
They must act now to press
for an immediate resolution of the dispute.
They need to obtain ironclad assurances that additional costs will be
borne by themselves, not by either federal,
state, or local governments or especially by Dulles Toll Road users who are
already stuck paying for half the$3 billion project. They should also make sure that forthcoming fines
are applied against the onerous debt laid on Dulles Toll road users over the
next four decades.
If our leaders don’t quickly
resolve this situation, the Silver Line may not open until next year and we may
pay millions of dollars through added tolls and taxes for the failure of MWAA
and Bechtel to meet their contractual obligations. At worst, MWAA and Bechtel may go to court,
putting completion of the project on hold indefinitely.
Our station is ready. Where are our Silver Line trains? (Robert Thomson/Washington Post) |
No comments:
Post a Comment
Your comments are welcome and encouraged as long as they are relevant, constructive, and decent.