Silver Line opening delayed until January, WTOP Exclusive, June 12, 2013

By Ari Ashe
WASHINGTON - Metro's Silver Line was expected to open this December, but a top official at the Metropolitan Washington Airports Authority now tells WTOP that the official launch date will not be until early next year.
Sam Carnaggio, director of the Dulles Corridor Project at MWAA, made the revelation during a presentation at the Action Committee for Transit on Tuesday.
"The project from the contractor is expected to be completed by the end of September or in early October, so we're now projecting January 2014," he says.
Carnaggio says construction work is about 94 percent complete, with the remaining work being mostly cosmetic. . . .