We are now less than a week away from the much anticipated
and long overdue opening of the Silver Line Phase 1 to Wiehle Avenue Station in
Reston. And yet, the County and state
have completed barely half the projects required to make the station and
Metrorail accessible, especially those for bicyclists and pedestrians.
First, let’s take a look at the key preparations that are in
place:
- The County has adjusted the Fairfax Connector
bus routes in and around Reston to deliver passengers to the station in a
largely zero-sum financial game. (Initially, it proposed taking more
money from Reston buses to apply to Tysons and McLean, but ultimately found
some other funding, at least for the reduced-fare Tysons circulators.) In
Reston, there will be slightly more frequent rush hour feeder service and new
mid-day routes, but there still are gaps in schedules and hours of service are
limited. There simply is not enough bus service to really encourage
Metrorail usage.
- The County has completed about 500’ of sidewalk
on the north side of Sunset Hills & west side of Wiehle to make
pedestrian/bicycle access possible to the Metro station.
- Comstock has met its various road improvement
obligations to upgrade intersections near the station (mostly at Wiehle and
Sunset Hills) under its public-private partnership (PPP) deal with the
County.
- Comstock has also
completed the underground parking garage required by the PPP, including 2,300
spaces for public Metro parking and 1,000 spaces it controls for future
tenants. It is charging as low as $4.50
per day for one of its parking spaces (more if you want special services
including guaranteed parking), thus undercutting the County’s $4.85/day charge
for its parking spaces right next door. (Note: The County
could have set its daily charge at any level. It chose go to with the
WMATA standard for Metro’s station garages.)
The latest available County tracking document shows there
are a total of 32 “spot” and “linear” projects, most of them recommended by
RMAG, that are needed for proper access to the station. What that document shows is that 12 of them
are complete, six of those by Comstock under its PPP agreement. The County document also shows that five
other projects (all to be done by Comstock—identified as “Dulles Rail Project”—should
have been done by May, and we suspect that they have been completed. All told, that’s 17 out of 32 projects
probably completed by the time Metrorail opens at the Wiehle station some nine
months late. We’re half way there!
So what’s missing six years after the RMAG report and nearly
a year after the Silver Line was supposed to open?
The most critical missing link, according to RMAG, and
one that is not even on the County list is the so-called Soapstone
Connector, the planned roadway/bridge/ped-bike route across the Dulles Corridor
from Sunrise Valley Drive to Sunset Hills.
Nonetheless, at this time, the County has picked a route and a
configuration for the Connector after conducting a feasibility study last year
(five years after the RMAG report). As
of this spring, it has budgeted only enough money through the end of the decade
to develop plans for the construction of this Connector.
The Soapstone Connector project won’t be built until at
least the next decade. Its
absence—likely for more than a decade—means that traffic going to/from the
Wiehle Silver Line station from the south as well as all traffic in both
directions trying to cross the Dulles Corridor or use the Dulles Toll Road from
Wiehle MUST use Wiehle Avenue. In
short, it will likely take as long to build this single bridge (from
feasibility study to opening, forget the 6-year old recommendation) as it will
take to complete the entirety of the Silver Line—and workday traffic will be
jammed the entire time.
So what is the status of the other Wiehle Station access
improvements?
All of the tasks the County lists that have not been completed except one
are the responsibility of the County (FCDOT).
Comstock has completed its obligations, the schedule indicates. The lone state project (VDOT) not yet
completed is crosswalks across Wiehle at Isaac Newton Square, which is scheduled
for completion next month. As for the
County’s eleven uncompleted projects (out of a total of 14):
- The earliest
to be completed will be four scheduled to be done in 2016,
including pedestrian intersection improvements on Town Center Parkway (in fact,
a Phase 2 project) in April 2016, intersection and sidewalk improvements done
by June 2016, and more pedestrian intersection improvements by October.
- Two more similar projects are scheduled for
completion in July 2017.
- The remaining five projects,
including a proposed grade-separate crossing for the W&OD trail across
Wiehle, have not yet been scheduled.
What is clear from this brief look at the projects and their
scheduling it the County has so far minimized its investment in improving
access to the Wiehle Metrorail station while talking incessantly about how
important the Silver Line will be to reducing area traffic.
That won’t happen if people can’t get there. Moreover, it will hinder developer interest
in building the transit-oriented development (TOD) in the station areas that
the County sees as a balm to its growing financial difficulties.
We think it would be better if the County put its money where its mouth
is. But then, maybe its financial "mouth" is only in Tysons Corner.